Below is a selection of available project profiles that Layfield has been involved in. The profiles provide brief descriptions often coupled with photographs of projects Layfield has done.   If you have any questions about specific projects or would like to discuss a project you are working on please feel free to contact us. Select from the links below to view our project profiles.

"Layfield Xtreme" Hoarding - Apartment Complex
LOCATION: Edmonton, AB
TIMEFRAME: November 2008
SCOPE OF WORK: Hoarding in four apartment complexes
PROJECT PARTNERS
Owner: Century Park
Client: Safway Scaffolding Installation: Safway Scaffolding
Material supplier: Layfield
24XT Geogrid Hwy 1 Pile Embankment
LOCATION: Trans Canada Highway 1- Sprott Street Overpass- Burnaby, BC TIMEFRAME: April 2011- June 2011
SCOPE OF WORK: Building up a pile embankment for highway overpass extensions with use of Mirafi’s 24XT geogrid
PROJECT PARTNERS:
Owner:PMH1- PK/F Joint Venture
Client: Peter Kiewit & Sons
Material supplier: Mirafi/ TenCate
60 mil RPP & CSPE for Water Reservoir Liner & Cover
LOCATION: Rancho Santa Margarita
TIMEFRAME: 2010 - 2011
SCOPE OF WORK:
244 million gallon reservoir
Reservoir area 900,000 SF
Liner: 60 mil RPP Tan/Black
Cover: 60 mil CSPE Tan/Black
18 hatches
71 "T" Vents
40 pumps
PROJECT PARTNERS:
Sukut Construction
Santa Margarita WD
Aqua Dam 10' - Mirimichi Golf Course
LOCATION: Millington, TN
TIMEFRAME: May 7th-May 12th 2011
SCOPE OF WORK: Provide 600 LF of 10’ high Aqua dam and Supervision to install.
PROJECT PARTNERS
Owner: Mirimichi Golf Course
Client: Justin Timberlake
Installation: Layfield Environmental
Material supplier: Aqua Dam Inc
Aqua Dam Flood Control - Burnaby 2007
LOCATION: Burnaby, British Columbia, Canada
TIMEFRAME: Spring 2007
PRODUCT; Flood Control Aqua Dams (3' high)
PROJECT PARTNERS:
Owner: City of Burnaby
Supplier: Layfield
Aqua Dam Flood Control - Manitoba 2011
LOCATION: Manitoba
TIMEFRAME: Jan - May 2011
SCOPE OF WORK: Design and Supply a Rapid Deployment Flood Protection System – Aqua Dam®
PROJECT PARTNERS:
Owner: Manitoba Infrastructure and Transportation
Installation: Layfield, Manitoba Infrastructure and Transportation Crews, Canadian Armed Forces, and Local Volunteers
Supplier: Layfield
Aqua Dam Flood Control - Red River 2009
LOCATION: Manitoba
TIMEFRAME: April 2009
PRODUCT: 250 Flood Control Aqua Dams - 3' by 100' Coffer Dams
PROJECT PARTNERS:
Owner: Government Regulator
Supplier: Layfield
Aqua Dam Flood Control - Spring 2011
LOCATION: On the Canadian Prairies
(Location withheld by owner’s request)
TIMEFRAME: Spring of 2011
SCOPE OF WORK: Aqua Dam for Flood Control
PROJECT PARTNERS:
Installation: Local road crews
Material supplier: Layfield
Aqua Dam® - Fuel Containment
LOCATION: British Columbia, Canada
TIMEFRAME: Fall 2004
SCOPE OF WORK: Installation of AquaDam to mitigate environmental damage caused by fuel & oil spill
PROJECT PARTNERS:
Contractor: Alpine Environmental
Aqua Dam® - Pipeline Crossing
LOCATION: Red Deer, AB
TIMEFRAME: Spring 2004
SCOPE OF WORK: Install of AquaDam for Pipeline work
PROJECT PARTNERS:
Owners: Pembina Pipelines
Contractor: Midwest General Contractors Ltd
Atlantis Matrix Tanks - New Development
LOCATION: Guelph, Ontario
TIMEFRAME: September 2010 – May 2012
SCOPE OF WORK: Supply of Atlantis Matrix Tanks to accommodate 1,240 m3 storage
PROJECT PARTNERS
Prior Construction Corp
IBI Group
First Capital Realty Inc
Layfield
Atlantis Storm Water Detention
LOCATION: Coquitlam, BC
TIMEFRAME: September, 2011
SCOPE OF WORK: Product training, Supply of Atlantis Storm Water Detention Tank materials, and Installation supervision
PROJECT PARTNERS
Client: Wolseley Waterworks
Engineer: Beesley Engineering
Installation: Tiegen
Material Supplier: Layfield Geosynthetics & Industrial Fabric Ltd
Atlantis Storm Water Detention - Shell Gas Station
LOCATION: Abbotsford, BC
TIMEFRAME: April 2010
SCOPE OF WORK: Supply Atlantis Stormwater Detention System, installation supervision
PROJECT PARTNERS:
Owner: Shell Canada Products
Client: Corix Water Products
Engineer: Hub Engineering
Installation: King Hoe Excavating
Supplier and Installation Supervision: Layfield
Baffle Curtain - City of London
LOCATION: London, Ontario
TIMEFRAME: Winter/Spring 2011
SCOPE OF WORK: 600 m long by 8.4 m high baffle curtain
PROJECT PARTNERS:
Owner: City of London
Contractor: McKay Cocker
Installation: Layfield
Baffle Curtain - Fixed
LOCATION: Ottawa, ON
SCOPE OF WORK: Fabricate and Install 53,800 ft2 Geomembrane Baffle Curtain
PROJECT PARTNERS
Contractor: Louis Bray Construction Ltd.
Material & Install: Layfield Environmental Ltd.
Baffle Curtain - Floating
LOCATION: Minnesota, USA
SCOPE OF WORK: Install of Engineered Baffle Curtain with Floatation System
PROJECT PARTNERS:
Owner: Food Processor
Baffle Curtain - Floating
LOCATION: Mississippi, USA
SCOPE OF WORK: Design & Install of 2,175 ft Baffle Curtain
PROJECT PARTNERS:
Owner: Pulp & Paper Mill Company
Baffle Curtain - Mechanically Fixed Tank
LOCATION: Corona, CA
TIMEFRAME: 6 Day Install
SCOPE OF WORK: Design & Install of Rigid Tank Baffle system
PROJECT PARTNERS:
Owners: Department of Water & Power
Contractors: Layfield Environmental Solutions
Decorative Pond c/w Hypalon Liner
LOCATION: Seattle, Washington
TIMEFRAME: Spring 2006
SCOPE OF WORK: Design & Install of 45 mil Hypalon Liner
PROJECT PARTNERS:
Owner: University of Washington
Egrid 170R Hwy 22 Bridge Abudment
LOCATION: Drayton Valley, AB
TIMEFRAME: October 2010
SCOPE OF WORK: An embankment for the new bridge needs to be built to crossover the North Saskatchewan River on hwy 22.
PROJECT PARTNERS:
Owner: Alberta Transportation
Client: MCL Group (sub for Graham Cons)
Installation: MCL Group
Material supplier: Layfield
E'Grid 2020 Biaxial GeoGrid - Bridge Expansion - Port Mann, Highway 1
LOCATION: Vancouver, BC
TIMEFRAME: 2009 - 2014
PRODUCT: E’GRID 2020 Biaxial geogrid
PROJECT PARTNERS
Contractors: Peter Kiewit/Flatiron Constructors
Installation: Peter Kiewit / Flatiron
EL6030 Liner - Soil Reclamation
LOCATION: Swan Hills
TIMEFRAME: January 2012
SCOPE OF WORK: Lease site soil reclamation
PROJECT PARTNERS
Distributor: National Oilwell
Client: IW Kuhn
EL6040 Black/White - Potable water storage liner & cover
LOCATION: South Australia
TIMEFRAME: June 2010
PRODUCT: 40 mil black Enviro Liner 6040 to line the pond. 40 mil white Enviro Liner 6040 to cover the pond
PROJECT PARTNERS
Owner: Roxby Downs Desalination Plant.
Material supply: Layfield
Installation: FABTECH
EL6040 Floating Cover for Glycol Recovery Pond
LOCATION: Lansing, Michigan
TIMEFRAME: 30 Days NTP/ Finish
SCOPE OF WORK: Design/Pre-con/Drawings/Submittals/Purchasing/Fabrication/Shipping/Installation/QC
PROJECT: 36,000 SF Glycol Recovery Pond EL 6040 Floating Cover
PROJECT PARTNERS: Capital Regional Airport Authority
Engineered Steel Containment System
LOCATION: Southern Ontario
TIMEFRAME: 3-4 Day Install
SCOPE OF WORK: Supply & install new secondary containment system to replace current substandard earthen berm
PROJECT PARTNERS:
Owners: Liquid Nitrogen Fertilizer Manufacturer
Enviro Liner & Arctic Liner - In-situ Oilsands Operation
LOCATION: Fort McMurray, Alberta
TIMEFRAME: July, 2002
PRODUCT: Enviro Liner®, Arctic Liner®, HDPE
PROJECT PARTNERS:
Owner: Suncor
Installer: Layfield
Enviro Liner 4000 - Frac Water Tank
LOCATION: NE British Columbia
TIMEFRAME: March, 2010
PRODUCT: Enviro Liner® 4030, Steel Water Tank (1.5 million liters capacity)
PROJECT PARTNERS:
Owner: Junior Oil and Gas producer
Supply and Install: Layfield
Enviro Liner 6000 - Frac Water Storage Pond
LOCATION: Horn River Basin, NE British Columbia
TIMEFRAME: January, 2009
PRODUCT: Enviro Liner® 6140,Geocomposite leak detection layer, Enviro Liner® 4040
PROJECT PARTNERS:
Owner: Petro Canada Limited
Design/Build: Layfield
Materials Supplier: Layfield
Enviro Liner 6000 - Golf Course Irrigation Reservoir
LOCATION: Uxbridge, ON
TIMEFRAME: Winter 2006 (10 day install)
SCOPE OF WORK: Manufacture & install flexible geomembrane reservoir liner
Enviro Liner 6000 - Irrigation Containment
LOCATION: Stouffville, ON
TIMEFRAME: February 2004
SCOPE OF WORK: Winter installation of 18,000m2 EnviroLiner 6030 for irrigation reservoir
PROJECT PARTNERS:
Owners: Clublink
Contractor: Hamilton Construction
Material Supplier: Layfield Environmental
Enviro Liner 6000 - Potable Water Tank
LOCATION: El Cajon, CA
TIMEFRAME: November 2007
PRODUCT: Enviro Liner 6030 cover, 36 mil RPP liner
PROJECT PARTNERS:
Developer: TC Construction
Supplier: Layfield
Enviro Liner 6000 - Suncor Temporary Secondary Containment Systems
LOCATION: Fort McKay, Alberta Canada
TIMEFRAME:June 2008 to present
SCOPE OF WORK: Temporary Secondary Containment System with Enviroliner
PROJECT PARTNERS / OWNER: Suncor Energy ( former Petro Canada site )
CLIENT: Suncor Energy
MATERIAL SUPPLIER: Layfield
Enviro Liner 6000HD - Secondary Containment for Deicing Fluids
LOCATION: London, Ontario
TIMEFRAME: August 2011
SCOPE OF WORK: Design, Supply and Installation of Secondary Containment System
PROJECT PARTNERS
Layfield Environmental Systems
Ministry of Transportation of Ontario
Enviro Liner 6040 - Sanitary Sewage Lagoon Upgrade
LOCATION: Township of Warwick, Lambton County Ontario
TIMEFRAME: November 2010
SCOPE OF WORK: Engineering design, Supply and Installation of lagoon lining and baffle curtain
PROJECT PARTNERS
Owner: Township of Warwick
Client: Van Bree Drainage and Bulldozing
Installation: EL6040-HD and XR-5 Baffle curtain
Enviro Liner 6040HD & LP 16 Non-woven - Fire & Irrigation Pond
LOCATION: Stanwood, WA
TIMEFRAME: October/November 2011
SCOPE OF WORK: EnviroLiner 6040HD Geomembrane and LP 16 Non-Woven Geotextile for a fire and irrigation pond.
PROJECT PARTNERS:
HD Fowler
Westcoast Excavators
Enviro Liner Geomembrane - Waste Water Treatment
LOCATION: South Australia
TIMEFRAME: December 2009
PRODUCT: Enviro Liner® Geomembrane
PROJECT PARTNERS
Geomembrane Supplier: Layfield
Installer: Geomate
Enviro liner30 mil - Snow Storage Facility
LOCATION: Edmonton, AB
TIMEFRAME: Summer 1999
SCOPE OF WORK: To line snow storage settling ponds with geomembrane for collection of heavy metals and road salts
PROJEECT PARTNERS:
Owner: City of Edmonton
EnviroLiner 4040 Underlay with Retaining Wall
LOCATION: Edmonton, AB
TIMEFRAME:
Oct. 2011 (Ponds 10,18 Liners)
Nov. 2011 (Liner and Walls)
SCOPE OF WORK: Enviro Liner 4040, LP8 underlay in Pond 10 (8,400m2) Pond 18 (2,300m2), and Retaining Wall at Pond 18
Green (1.35m high – 9 blocks high, includes LP30T geogrid, drainage gravel, etc).
PROJECT PARTNERS
Owner: Royal Mayfair Golf Course Client: Royal Mayfair GC
Installation: Oct-Dec 2011
Material suppliers: Layfield PolyFilms, Expocrete (Pisa stone), Mirafi (Geogrid)
EnviroLiner 6040 Modular Insulated Cover - Sewage Lagoon
LOCATION: Entwistle, AB
TIMEFRAME: Oct-Dec ‘10
INSTALL: June '11
SCOPE OF WORK:EL6040 MIC’s (with RMER foam) XR5 Baffles
PROJECT PARTNERS:
Owner: Parkland County
Client: Gabriel Construction
Installation: Layfield ESL
Material supplier: Layfield GIF, Beaver Plastics
Environmental Geomembrane Upgrade - Methanex Plant Restart
LOCATION: Medicine Hat, AB
TIMEFRAME: August 2010 – July 2011
SCOPE OF WORK: Enviro Liner & Non Woven Geotextile within Tankfarms, Water Ponds, Wastewater Ponds and Rail Track Loading Containment
PROJECT PARTNERS
Owner/Client: Methanex Corporation
Installation: Layfield Environmental
Material supplier: Layfield Environmental
EnviroSlope Geogrid Wrap - Railway Trestle
LOCATION: Southern Ontario
SCOPE OF WORK: EnviroSlope Geogrid Wrap face slope to replace wooden railway trestle
PROJECT PARTNERS:
Owner: St. Lawerence & Hudson Railway
EnviroSlope Geogrid Wrap - Victoria Park Road Slide
LOCATION: Edmonton, AB
TIMEFRAME: Summer 1998
SCOPE OF WORK: Geosynthetic reinforced slope using polyester geogrids
PROJECT PARTNERS:
Owners: City of Edmonton
EnviroSlope Geoweb Face - Anthony Henday Drive
LOCATION: Edmonton, AB
TIMEFRAME: 2004 - 2005
SCOPE OF WORK: EnviroSlope Geoweb Face steeped slope along concrete culvert
PROJECT PARTNERS:
Owners: City of Edmonton & Province of Alberta
Floating Cover - A New Odor Control and BioGas Collection Cover
SCOPE OF WORK: Manure Management
SPECIES: Dairy, Beef, Swine
TECHNOLOGY CATEGORY: Biogas Collection Pond Cover
Floating Cover - Cargill Anaerobic Cover
LOCATION: High River, AB
TIMEFRAME: Summer 2004
SCOPE OF WORK: Design & install anaerobic floating cover system with anchor system and gas collection piping.
PROJECT PARTNERS:
Owners: Cargill Foods
Floating Cover - El Toro Water District
LOCATION: Lake Forest, CA
TIMEFRAME: 2002
SCOPE OF WORK: Fabricate and install liner and cover for districts water reservoir
PROJECT PARTNERS:
Owner: El Toro Water District
Floating Cover - Household Sewage Lagoon
LOCATION: Fort St. John, BC
TIMEFRAME: June 2009
PRODUCT: Hazgard 535
PROJECT PARTNERS
Owner: Private Household (Kimberly Gulevich)
Supply and Install: Layfield
Floating Cover - Potable Water Reservior
LOCATION: Middleton, NS
SCOPE OF WORK: Install 45 mil polypropylene flexible floating cover system for 1,000,000 gallon potable water reservoir
PROJECT PARTNERS:
Owners: Town of Middleton, NS
Floating Cover - Tensioned Cable System
LOCATION: Poway, CA
SCOPE OF WORK: Floating cover replacement - water treatment plant
PROJECT PARTNERS:
Owner: City of Poway - Lester Bergland Water Treatment Plant
Floating Cover - Truckee Meadows
LOCATION: Reno Nevada
TIMEFRAME: Winter 2004
SCOPE OF WORK: Hypalon Cover - Reinforced Polypropylene Liners with leak detention
PROJECT PARTNERS:
Owner: Truckee Meadows Water Company
Contractor: CW Neal
Floating Cover and Liner for Water Reservoir
LOCATION: City of Astoria, Oregon
TIMEFRAME: July - October 2009
PRODUCT: Geomembrane, Floating Cover, and Lining System
PROJECT PARTNERS:
Owner: City of Astoria
Engineer: MWH
Materials Supplier: Layfield
Installation: Layfield
Floating Cover for Potable Water Reservoir
LOCATION: Pacific Palisades, CA
TIMEFRAME: January 2011 – June 2011
SCOPE OF WORK: Furnish and install 45 mil CSPE custom color floating cover system, chaffer strip, and cover appurtenances
PROJECT PARTNERS:
Owner: Los Angeles Department of Water and Power
Client: LADWP Installation: Layfield Environmental Systems Corp
Material supplier: Burke Industries
Floating Cover M.I.C. - Tulalip Fish Hatchery
LOCATION: Tulalip, Washington
TIMEFRAME: December 2006
SCOPE OF WORK: Design and install insulated cover for fish hatchery to ensure maintained water temperatures and minimize debris infiltration
PROJECT PARTNERS:
Owner: Tulalip Fish Hatchery
Floating Cover Maintenance
LOCATION: Luray, VA
TIMEFRAME: Summer/Fall 2004
SCOPE OF WORK: Maintenance of Hypalon Floating Cover & Hardware
PROJECT PARTNERS:
Owner: City of Luray
Contractor: Layfield/CW Neal
Floating Cover Replacement - City of Ogden
LOCATION: Ogden UT
TIMEFRAME: August - October 2011
SCOPE OF WORK: Replace 3 towered tensioned 45 mil floating covers with a perimeter skirt upgrade
PROJECT PARTNERS
Owner: City of Ogden
Installation: Layfield Environmental Systems Corp
Engineer: Sunrise Engineering
Floating Silt Barrier - Burnaby Lake Rejuvenation Project
LOCATION: Burnaby, BC
TIMEFRAME: January – June 2010
SCOPE OF WORK: 4,600 lineal Meters of Floating Silt Barrier
PROJECT PARTNERS
Owner/Client: Hazco Environmental Services
Floating Silt Curtain Anthony Henday Bridge
LOCATION: Edmonton, AB
TIMEFRAME: Six month use of floating curtain
SCOPE OF WORK: Supply Floating Silt Curtain (FSC) to contain silt & sediment released during construction or Anthony Henday Bridge
PROJECT PARTNERS:
Owners: The City of Edmonton & Province of Alberta
Floating Silt Curtain Used at McGregor Lake
LOCATION: McGregor Lake, AB
SCOPE OF WORK: Supply 25' deep Floating Silt Curtain (FSC)
PROJECT PARTNERS:
Owner: Alberta Transportation
Floating Silt Curtain Used in Outfall Reconstruction
LOCATION: Edmonton, AB
SCOPE OF WORK: Suply 7' Deep Floating Silt Curtain Monofilament Geotextile
PROJECT PARTNERS:
Owner: City of Edmonton
Frac Water Containment System
LOCATION: Various locations in the Western Canada Sedimentary Basin
TIMEFRAME: February – March 2011
SCOPE OF WORK: Frac Water Storage Tank Liner
MATERIALS: 140’ x 140’ stepped tabbed liner EL 4030
PROJECT PARTNERS
Owners: Poseidon Concepts
Material supplier: Layfield
Geoblock Permeable Paving for Private Residence
LOCATION: Private Residence, Crescent Beach, Surrey, B.C., Canada
TIMEFRAME: April 2011
SCOPE OF WORK: Excavate existing sod and other organic materials, install sub-grade , GEOBLOCK permeable paver system & new sod
PROJECT PARTNERS:
Owner: Mr. & Mrs. Rose
Client: Took Engineering
Installation: Martin Pro Builders
Material supplier: Layfield Geosynthetics / Presto Geosystems
Geosynthetic Containment System - Concrete Cover
LOCATION: West of Conklin, AB
TIMEFRAME: April – November 2009
SCOPE OF WORK: Earthworks, survey, piping, geosynthetic containment system, concrete cover
PROJECT PARTNERS
Owner: Statoil
Prime Contractor:
IMV Construction
General Contractor: Layfield
Geoterra- Sulpher Block Walkway
LOCATION: Cremona, AB
TIMEFRAME: Spring 2009
PRODUCT:
GEOTERRA
LP16 Non-Woven Geotextile
Smooth HDPE 60 mil
PROJECT PARTNERS:
Owner: Shell Canada Energy
Installation: Layfield
Geotube Shell Scotford Effluent Pond De-Sludging
LOCATION: Ft Saskatchewan, Alberta
TIMEFRAME: April – May 2012
SCOPE OF WORK: Removal of Accumulated Sludge from Effluent Holding Pond & Effluent Release Pond
PROJECT PARTNERS:
Owner: Shell Canada Energy
Geotube® Supplier: Tencate
Polymer Supplier: WaterSolve LLC
Pump Supplier: Canadian Dewatering
Dewatering Contractor: Layfield Environmental Systems Ltd.
Geoweb GW30V6 & LP45G High STrength Geotextile
LOCATION: Lloydminister, AB
TIMEFRAME: June 2009
PRODUCT: Geoweb GW30V6 & LP45G High Strength Geotextile
PROJECT PARTNERS:
Owner: Oil and Gas Producer
Supplier: Layfield
Geoweb Slope Protection for Stormwater Pond
LOCATION: Conklin, AB
TIMEFRAME: Project start /end - Feb. 4, 2011 to March, 2011
SCOPE OF WORK: Provide slope protection for a 21,000 cubic metre capacity Stormwater Pond with clay liner and 3H:1V slopes
PROJECT PARTNERS
Owner: FCCL Oil Sands Partnership (Cenovus Energy and Conoco Phillips)
Client: Browns Bobcat Service
Installation: Browns Bobcat Service
Material supplier: Layfield / Presto Geosystems
Hazgard 100 Vapor Barrier - Refilling Station
LOCATION: Markham, Ontario
TIMEFRAME: October 2011
SCOPE OF WORK: Supply and Installation of HZ100 and LP16 beneath the Convenience Store and all Site Servicing Utilities
PROJECT PARTNERS
Imperial Oil Limited
Barenco an exp Company
ECS Engineering and Construction
Hazgard 1000 - Containment of Fuel Tank Farm
LOCATION: Voisey's Bay, Labrador, NL
TIMEFRAME: November 2003
SCOPE OF WORK: Containment of a Gasoline & Diesel Fuel Tank Farm
PROJECT PARTNERS
Owner: INCO - Voisey's Bay
Contractors: IKC Borealis
Hazgard 250 - Underground Fuel Tanks
LOCATION: Port Hadlock, Washington
TIMEFRAME: November 15th / January 20th
SCOPE OF WORK: Layfield supplied and directed the installation of Hazgard 250 geomembrane to encapsulate 2 underground fuel tanks.
PROJECT PARTNERS
Owner: Kroger Foods
Installation: Evergreen Environmental and Layfield Environmental
Material supplier: Layfield Environmental Systems
Hazgard Liner - Soil Remediation
LOCATION: Vancouver, BC
SCOPE OF WORK: Supply Hazgard 100 for soil remediation
PROJECT PARTNERS:
Owner: Private Developer
Engineer: NEXT Environmental
Contractor: Safety Kleen
Supplier: Layfield
HDPE 80 mil Floating Covers - CCD Tank
LOCATION: Key Lake, Saskatchewan
TIMEFRAME: Fall 2011 – Spring 2012
SCOPE OF WORK: Design of Floating Cover over CCD Tank
PROJECT PARTNERS
Cameco Corp MDH Engineering
Saskachewan Red Engineering
Edmonton North West Hydraulic Consultants (NHC)
HDPE StudLiner
LOCATION: Foster Creek, AB
SCOPE OF WORK: Provide 80 mil HDPE Studliner for primary & secondary containment of mud storage cells
PROJECT PARTNERS
Owner: EnCana Oil & Gas Partnership
Supplier: Layfield
HSWG & Geogrid Deployment
LOCATION: Fort McMurray, Alberta
TIMEFRAME: December 2011 – March 2012
SCOPE OF WORK: Deployment of 750,000 m2 of HSWG along with Geogrid
Hypalon 45 Floating Cover - Service & Maintenance Program
LOCATION: Grand Forks, BC
SCOPE OF WORK: Inspect condition of 30 year old Mechanically Tensioned cover system and repair where necessary
PROJECT PARTNERS:
Owner: City of Grand Forks
Insulated Cover "Algae Control"
LOCATION: Fruitlanndd, Iaho
SCOPE OF WORK: Manufacture and supply custom insulated floating cover system
PROJECT PARTNERS:
Owner: City of Fruitland
Consulting Engineer: Holladay Engineering Company
Supplier: Layfield
LP8 Rough Grading - Highway 63
LOCATION: Highway 63, Northern Alberta
TIMEFRAME: February 2011 – April 2011
SCOPE OF WORK: Rough grading of Highway 63, required 1,318 rolls of LP 8.
PROJECT PARTNERS
Owner: Alberta Transportation
Installation: Thompson Bros. Construction Ltd.
Material supplier: Layfield Geosynthetics & Industrial Fabrics Ltd.
Methane Vapor Barrier
LOCATION: Calgary, AB
SCOPE OF WORK: Under-building methane collection system design and install
PROJECT PARTNERS:
Owner: Calgary Regional Health Authority
New BioGas to Utility System
LOCATION: Riverdale, CA
TIIMEFRAME: January 2008
SCOPE OF WORK: Design and install flexible gas collection floating cover for digesters
PROJECT PARTNERS:
Owner: Bio Energy Solutions
Supplier: Layfield
North Vancouver Remediation Site
LOCATION: Burrard Inlet, North Vancouver BC
SCOPE OF WORK: LP6, OR RPE 25 & Actic Liner used in soil and water remediation application
PROJECT PARTNERS:
Next Environmental Inc.
Safety Kleen Ltd.
Polypropylene - Cold Temperature Installation
LOCATION: Northwest Territories
TIMEFRAME: Winter-Spring 2001 & 2002
SCOPE OF WORK: Supply, fabricate & install 32,000m2 of 40 mil polypropylene for collection dam
PROJECT PARTNERS:
Owners: BHP Diamond Mine
Engineer: EBA Engineering Consultants Ltd.
Contractor: Layfield Environmental
Prefabricated Liner for Fish Farm
LOCATION: Miami FL
TIMEFRAME: December 2011
SCOPE OF WORK: Furnish & Install Liner for Fish farm
PROJECT PARTNERS:
Owner: Sun AquaPonics
General Contractor: Layfield Environmental
Secondary Containment Lining System
LOCATION: Edmonton, AB
Suncor Edmonton Refinery, formerly Petro Canada Refinery
TIMEFRAME: October 2010 – March 2011
SCOPE OF WORK: Supply and Install Secondary Containment Lining System
PROJECT PARTNERS
Owner: Suncor Energy
Engineer: TWD Technologies
Contractor: CPI Construction Installation: Layfield Environmental
Material supplier: Layfield Environmental
Single Wall Emulsion Liner
LOCATION: Diavik, Northwest Territories
SCOPE OF WORK: Manufacture and supply 15" x 100' 8mil emulsion liner
PROJECT PARTNERS:
Owner: Diavik Diamond Mines
Soil Reinforcement for Temp. Housing & Landfill Expansion
LOCATION: Slave Lake, Alberta
TIMEFRAME: May 2011- Oct. 2011
SCOPE OF WORK: Soil reinforcement for temporary family housing. Landfill expansion.
PROJECT PARTNERS
Manager: Ken Hedin
Client: Apex Distribution
Installer: Seguin Construction & Focus Corp.
Spray Applied Geomembrane
LOCATION: Edmonton, AB
SCOPE OF WORK: Secondary containment through Permax 700 Polyurea Spray Applied geomembrane
PROJECT PARTNERS:
Owner: ATCO Pipelines
Spray Applied Secondary Containment Liner
LOCATION: Hinton, Alberta
TIMEFRAME: January – February 2012
SCOPE OF WORK: Installation of Secondary Containment Liner within a Westeel Containment System
PROJECT PARTNERS
Owner: Secure Energy Services
Material Supplier and Installer: Layfield Environmental Systems Ltd.
Steel Containment System - Fresh Water
LOCATION: Near Ft. St. John, BC
TIMEFRAME: May 2011
SCOPE OF WORK: Design and fabrication of a fresh water storage system for 4600 m3
PROJECT PARTNERS:
Owner: Oil and Gas Producer
Installation: May 2011
Material supplier: Layfield
StormChamber - Conestoga College
LOCATION: Cambridge, Ontario
TIMEFRAME: September 2010
SCOPE OF WORK: 700m3 StormChamber System
PROJECT PARTNERS:
Owner: Conestoga College
Client: VanBots/Carillion
Installer: Groundworks Construction
Super-Layflex Stretch Hooder Film
LOCATION: Toronto, ON / East Moline, IL / Camp Hill, PA / Lagrange, GA /
Northglenn, CO
TIMEFRAME: October 2010 – April 2011
SCOPE OF WORK: Develop lighter gauge & tougher stretch hooder film
PROJECT PARTNERS:
Customer Name: National Packaging Specialists / Atlas Roofing
Tailings pond rehabilitation
LOCATION: Northern Alberta (Oilsands)
TIMEFRAME: Winter 2010
PRODUCT: High Strength Geotextiles
PROJECT PARTNERS:
Material Supplier: Tencate Mirafi
Fabrication and Installation: Layfield
Turbidity Barrier - OPG HydroElectric Facility
LOCATION: Stoney Falls, Ontario
TIMEFRAME: June 2010 – 2015
SCOPE OF WORK: Turbidity Barrier Installation for Sediment Control
PROJECT PARTNERS:
Ontario Power Generation
Layfield
KAP Kiewit Alarie Partnership
Battlefield Equipment Rentals
Turbidity Barrier - Sediment / Pollutant Containment
LOCATION: Seattle, WA
SCOPE OF WORK: Desgin & supply Type 2.DOT approved turbidity barrier system
Turbidity Barrier - Sediment Control for Mining Operations
LOCATION: Northwest Territories
TIMEFRAME: Spring 2007
SCOPE OF WORK: Supply a silt and sediment containment system for mining project
Turbidity Curtain - Davy Crockett Shipwreck
LOCATION: Washougal, WA (Columbia River)
TIMEFRAME: April 2011
SCOPE OF WORK: 2400 Linear Feet Type 1 Turbidity Curtain (30-40 ft deep)
PROJECT PARTNERS:
Owner: US Coast Guard
Client: Bergerson Construction
Supplier: Layfield
Under Building Petroleum Vapor Barrier - Avalon Bay
LOCATION: Bellevue, Washington
TIMEFRAME: June 2006
SCOPE OF WORK: Design and install petroleum capable membrane for vapor barrier and extraction
PROJECT PARTNERS:
Owner: Avalon Bay Communities Inc.
Unsupported Polyproplylene 40mil - Containment
LOCATION: Washington State
SCOPE OF WORK: Replace existing liner system in two above ground tank containment systems
PROJECT PARTNERS:
Owner: North West Chemical Company
Contractor: Layfield Environmental Systems
Vertical Wick Drain Supply & Install
LOCATION: CFB- Esquimalt Victoria International Airport, Victoria, BC
TIMEFRAME: November 2011- January 2012
SCOPE OF WORK: Supply/ Install - Vertical Wick Drain
PROJECT PARTNERS
Owner: Dept National Defense
Design Consultant: Stantec
Contractor: Knappett Projects
Vertical Wick Drains - Red River Floodway
LOCATION: Winnipeg, MB
TIMEFRAME: July 2007
SCOPE OF WORK: Installation of vertical wick drains for construction of railway embankment across Red River Floodway.
PROJECT PARTNERS:
Contractor: Hugh Munro Construction Ltd.
Supplier: Layfield Environmental Systems
XR-5 Vapor Barrier
LOCATION: La Mesa, CA
TIMEFRAME: April 2009
PRODUCTS: XR-5 Vapor Barrier
PROJECT PARTNERS
Owner: Starbucks
Contractor: Kahl Construction
Installation: Layfield